Tidewater Bridge Construction PDF  | Print |  E-mail

Please refer to the links below for additional information about the Mill Creek Bridge closing [Tidewater Drive bridge].

Warwick Beacon articles:

"Open again", Warwick Beacon 9/15/2015

"Pushing for opening of Mill Cove bridge", by John Howell, 8/25/15.

"Bayside sewer project paying close attention to rich Native American past", by John Howell, 7/7/15

"Delay in bridge opening may be long-term benefit", by John Howell, 6/23/15

"City expects winter will not delay Mill Cove Bridge project", by John Howell, 3/12/15.

"Bridge out for 9 Months", by John Howell, 9/18/14.

"Mill Creek Bridge construction starts September 22" [2014], 9/11/14

Tidewater Drive Bridge Progress Photos. The most recent photos taken are presented first.
Scroll down to see earlier periods.

Let 'em roll... Bridge re-opens on Septemeber 11, 2015!
It's not a 100% finished but close enough. Yippee! Thank you!

Tidewater Re-Opens
Tide was quite high when I took the photo on 10/4/15.

August 30, 2015:
View from the water very close to high tide (close to full moon).

twbridge-083015-1

Side rail detail. Hoping that zig-zaggy line (near water bottle) is just a surface/color variation from the forms and not a crack.
twbridge-083015-2

August 1,2015:
Concrete in process!

twbridge-080115-1

twbridge-0080115-2

twbridge-080115-3


July 23, 2015:

Deck work.

twbridge-072315-1

twbridge-072315-2

July 19, 2015:
Cove view from my paddleboard. Fairly close to high tide. Maybe 15 - 20 minutes after peak.

twbridge-071915-1

twbridge-071915-2

June 27, 2015:
Getting there... errrrr ummmm, I think? Natural Gas piping work in the street started this week too. Probably getting close to getting rid of that temporary "thing" running on top of the bridge.
Pretty sure that isn't a new handrail LOL! Looks pretty similar to last week but there was quite a bit of activity there this week.

twbridge-062715-1

twbridge-062715-2

twbridge-062715-3

June 22, 2015:
More form construction in progress.
twbridge-062215-1

twbridge-062215-2

twbridge-062215-3

June 13, 2015:
A little more form construction in progress.
twbridge-061315-1

twbridge-061315-2

twbridge-061315-3

June 7, 2015:
twbridge-060715-1

twbridge-060715-2


May 27, 2015:

twbridge-052715-1

twbridge-052715-2


May 18, 2015:

twbridge-051815-1

twbridge-051815-2


May 3, 2015:

twbridge-050315-1

twbridge-0050315-2


April 11, 2015 (After the snow melt)

Piling Driving:
twbridge-041115-1

twbridge-041115-2


Fall 2014 - Photos of bridge demo & the beginning of re-routing/temporary utilities: